A factory solar installation can generate electricity for decades, but its inverter may need attention sooner than its rooftop modules. Replacing a faulty unit involves more than choosing a new box: UK manufacturers need to consider lost generation, electrical compatibility, safety, grid-connection conditions, warranties and operational downtime.
This practical guide complements our solar panels for factories guide and commercial solar maintenance checklist.
What does a factory solar inverter do?
Solar panels generate direct-current electricity. The inverter converts it into alternating current suitable for use in a factory and, where permitted, export. It also provides monitoring, control and protection functions. Some factories have multiple string inverters; others use centralised arrangements. A failure may therefore affect part or all of the generation.
Five signs an inverter needs professional assessment
- Repeated fault codes or shutdowns: Record codes and conditions instead of repeatedly resetting equipment.
- Unexpected generation shortfall: Compare output with irradiance, temperature, season and historical performance.
- Cooling problems: Overheating alarms, damaged fans and blocked airflow need investigation.
- Communication failures: Missing monitoring data does not necessarily mean lost generation.
- Obsolete equipment: Unavailable spares can make planned replacement preferable to a lengthy breakdown.
Only competent personnel should inspect, isolate or test the equipment. PV circuits may remain hazardous even with the AC supply switched off.
Repair, like-for-like replacement or upgrade?
Repair can be appropriate if the cause is understood, manufacturer-supported parts are available and safe recommissioning is possible. Compare diagnosis, labour, parts, testing and warranty support.
Like-for-like replacement can reduce redesign, but matching AC power ratings alone is insufficient. Check DC voltage/current ranges, string configuration, MPPT inputs, communications, ventilation, protection and manufacturer instructions.
Upgrade or redesign may be worthwhile when monitoring is inadequate, equipment is obsolete, arrays have changed or batteries are being considered. Any alteration to export behaviour, rating or protection can introduce new engineering and DNO requirements.
UK DNO and G99: check the original approval
Before ordering equipment, review the existing connection agreement, inverter schedule, commissioning records and export-limitation arrangements. Identify the distribution network operator (DNO) and assess whether the proposed replacement changes generating capacity, protection settings or export controls.
The correct approval or notification process is site-specific. Neither “every replacement needs a new application” nor “replacements never require DNO involvement” is a safe blanket rule. Obtain documented advice and written DNO confirmation where necessary before carrying out consent-dependent work. Read the factory solar DNO and G99 guide and the Energy Networks Association guidance.
What affects UK factory inverter replacement costs?
There is no credible universal UK price: a small single-unit replacement and a multi-inverter industrial project differ considerably. Request itemised quotations covering:
- Inverter equipment, compatibility, lead time and warranty.
- Engineering surveys, DC/AC checks, protection and DNO correspondence.
- Access, lifting, isolation, removal, disposal, cabling and switchgear work.
- Commissioning, testing, settings, monitoring integration and handover.
- Generation downtime and potential interruption to factory operations.
- Future servicing and spare-parts support.
Compare proposals on a consistent scope and whole-life cost rather than equipment price alone.
Calculate the cost of lost solar generation
A useful first-pass calculation is lost usable solar generation (kWh) × value per lost kWh, plus directly attributable operational costs. The unit value depends on whether electricity would have been consumed onsite or exported.
For illustration, if a shutdown prevents 2,000 kWh that would otherwise have been used onsite, and the avoidable import cost is 18p/kWh, potential lost savings equal £360. This is not a forecast. Check actual generation, demand, tariffs and export arrangements. Where only one inverter is affected, calculate the relevant proportion rather than assuming the entire system is offline. See our half-hourly electricity data guide.
Plan the work around production
Agree isolation boundaries, permits to work, access, site safety and the production timetable in advance. Coordinate with facilities, maintenance, health and safety and insurers where relevant. Determine whether switchboards, emergency arrangements, roof access or fire strategy will be affected. Review HSE roof-work guidance and our factory solar fire-safety checklist.
Seven-point replacement checklist
- Gather drawings, commissioning certificates, warranties, DNO approval and monitoring data.
- Commission competent diagnosis to distinguish inverter faults from grid, cable, protection and communication issues.
- Compare repair, equivalent replacement and upgrade options.
- Confirm DC/AC compatibility, protection, safety and DNO approval or notification requirements.
- Estimate generation losses and agree a production-compatible work window.
- Require documented commissioning, updated drawings, monitoring and warranty information.
- Check performance after return to service and update the maintenance plan.
Should you add a battery during inverter replacement?
Replacement can be an opportunity to assess storage, but should not automatically trigger a battery purchase. Review half-hourly demand, export limits, round-trip losses, battery operation, project costs and DNO implications. Read the UK factory battery storage guide.
Frequently asked questions
How long does a commercial solar inverter last?
It varies by design, conditions, maintenance and manufacturer support. Track fault history, temperatures, output and spare availability rather than assuming a fixed replacement year. Historic England’s PV maintenance guidance notes that inverters typically have a shorter service life than PV modules.
Can the factory keep operating during replacement?
Often, but the electrical arrangement determines whether isolation affects only the PV system or wider factory operations. Require an approved method statement.
Does replacing an inverter mean replacing the panels?
Not necessarily. Existing modules may remain suitable if the new inverter is compatible with the array, cabling, protection and relevant standards.
Should a replacement inverter be larger?
Only if engineering and financial analysis support it. A larger AC rating does not automatically increase useful generation and may affect grid permissions.
Protect the value of your factory solar system
Treat inverter replacement as planned asset management, not an emergency purchasing exercise. Good records, realistic downtime planning and early compliance checks can help avoid unnecessary cost and disruption. Contact Commercial Solar Systems to discuss a factory solar assessment or replacement planning.
Further technical reading: Solar Energy UK rooftop O&M guidance; ENA distributed-generation guidance; HSE HSG33. Check current standards and site-specific DNO conditions.