Factory Solar Self-Consumption: How UK Manufacturers Should Analyse Half-Hourly Demand

A factory can have an excellent solar roof and still buy substantial amounts of electricity during its busiest production hours. One reason is simple: electricity demand and solar generation do not always peak together. Before approving a rooftop PV project, UK manufacturers should examine half-hourly electricity data and identify when the factory actually consumes power.

Why a factory’s load profile matters

Annual electricity consumption alone cannot show how much solar power a site will use. Two factories buying the same annual kWh may have very different operating patterns. A single-shift engineering workshop may consume most power between 7am and 5pm; a refrigerated food facility may run significant loads overnight and at weekends. Solar generation varies with daylight, season, weather, orientation and shading. The financially useful question is how much generation coincides with site demand, after accounting for export and any operational restrictions.

1. Obtain a representative half-hourly dataset

Ask your energy supplier, meter operator or energy-management team for at least 12 months of half-hourly import readings where available. The period should include normal production, shutdowns, holidays, maintenance and seasonal changes. Record data gaps, meter changes, unusual outages and major new equipment. If only shorter data is available, label the uncertainty rather than treating it as a full-year forecast.

Also collect electricity tariffs and standing charges, time-of-use rates where applicable, maximum import demand, any export arrangements, and the site’s production calendar. The half-hourly dataset should be reconciled against bills before it becomes the basis of an investment case.

2. Separate weekday, weekend and shutdown demand

Plot a typical weekday and weekend profile for each season. Identify the base load that continues while production stops, and the additional load created by machinery, compressed air, extraction, heating, cooling and charging. A factory that closes for two weeks in August may export more solar electricity during those weeks. A seven-day food-processing operation may have a more consistent daytime demand.

Do not assume a 24-hour factory will consume all its solar output: night-shift electricity use does not overlap with daylight generation unless storage or flexible processes are involved.

3. Compare hourly generation and demand, not just annual totals

Ask the installer for a credible solar generation model that accounts for roof orientation, pitch, shading, system losses and local conditions. Compare generation and import demand at matching time intervals, adjusting for any expected process changes. The model should estimate the electricity used on site, exported and potentially curtailed, with clear assumptions.

Illustrative example only: if a factory produces 200,000 kWh of solar electricity in a year, and 150,000 kWh coincides with demand that would otherwise be imported, the modelled self-consumption is 75%. The remaining 50,000 kWh may be exported or curtailed, subject to connection and commercial arrangements. These figures are an arithmetic illustration, not a performance prediction.

4. Stress-test production changes

Solar should be assessed against the factory’s realistic future operation, not only last year’s pattern. Test a second shift, a shorter working week, a major refrigeration upgrade, a new CNC line, planned electrification and potential relocation. For each scenario, show how onsite use, exports, grid imports and financial returns change.

Our factory solar business-case stress-test explains how to challenge electricity price, shift-pattern and export assumptions before investing.

5. Check roof and electrical constraints before final sizing

A load profile is not a structural survey or connection approval. A viable design also needs roof-condition and loading checks, safe access, fire and insurance considerations, switchgear and transformer capacity, and appropriate Distribution Network Operator (DNO) assessment. Oversizing purely to maximise annual generation can produce weaker returns if exports are worth substantially less than avoided imports.

Start with our solar panels for factories guide for the wider feasibility process, and read the factory transformer and LV/HV capacity checklist before finalising the electrical design.

6. Compare finance options using the same underlying assumptions

Whether a business purchases solar outright, finances the installation or agrees a power purchase agreement (PPA), use consistent assumptions for generation, self-consumption, export, maintenance and degradation. Include contract length, price escalators, ownership, repair responsibilities and termination terms. Do not confuse a low advertised electricity price with a guaranteed saving across every hour of operation.

Questions to ask before signing

  • Have we reconciled the half-hourly data with actual electricity bills?
  • What percentage of generation is forecast to be used on site, and why?
  • How do weekends, bank holidays and planned shutdowns affect exports?
  • What happens to returns if our shift pattern changes?
  • Are grid connection, roof repairs, maintenance and inverter replacement included?
  • Can we see conservative, central and optimistic scenarios?

What a good factory solar proposal should show

A decision-ready proposal explains its input data, generation method, hourly matching assumptions, engineering constraints and financial sensitivities. It should identify what has been measured, what has been modelled and what still needs professional assessment. That evidence makes it easier for operations, finance and facilities teams to compare proposals on a like-for-like basis.

For an initial estimate, try the commercial solar calculator, then contact Commercial Solar Systems for a site-specific assessment. A calculator is a starting point, not a substitute for half-hourly modelling and roof and electrical surveys.

Factory Solar in Winter: How UK Manufacturers Should Budget for Seasonal Generation

UK manufacturing factory with solar panels on a pitched metal roof and engineers reviewing project plans

Factory Solar Business Case: Stress-Test Electricity Prices, Production Shifts and Export

Categories:

Share :

Factory Solar in Winter: How UK Manufacturers Should Budget for Seasonal Generation

UK manufacturing factory with solar panels on a pitched metal roof and engineers reviewing project plans

Factory Solar Business Case: Stress-Test Electricity Prices, Production Shifts and Export